SOLAS CHAPTER XII - ADDITIONAL SAFETY MEASURES FOR BULK CARRIERS
- APPLICABLE TO BULK CARRIERS(means ships constructed with single deck, top-side tanks and hopper side tanks in cargo spaces and intended primarily to carry dry cargo in bulk; or ore carriers; or combination carriers.
- IN FORCE FROM 01 JUL 1999 Depending on Ship's Age as per Reg 3
- Regulations categorise Bulk Carriers as Single skin & Double skin Bulk Carriers loading Bulk Cargoes in two density groups 1000 kg/m3 and 1780 kg/m3 and above.A standard length of 150 meters is used as a basic length.This length appears in loadline certificate.
- SINGLE SIDE SKIN BULK CARRIER
- ANY PART OF CARGO HOLD IS SHIP'S SIDE SHELL
- IF ANY AREA(ballast tank/cofferdam etc) IS SEPARATING CARGO HOLD FROM SIDE SHELL(ship side),THEN PERPENDICULAR DISTANCE BETWEEN SIDE SHELL & CARGO HOLD IS LESS THAN 760 mm(for ships built before 01 jan 2000), 1000 mm(for ships built before 01 jan 2006 but after 01 jan 2000)
- DOUBLE SIDE SKIN BULK CARRIER
ANY BULK CARRIER WHICH IS NOT A SINGLE SKIN BULK CARRIER.
So,SOLAS stipulates following requirements:-
Bulk carriers of 150 m in length and upwards of single-side skin construction,
designed to carry solid bulk cargoes having a density of 1,000 kg/m3
and above, constructed on or after 1 July 1999
- When loaded to summer loadline,be able to withstand flooding in any compartment and be able to float with following stability criteria:-
- The final waterline after flooding, taking into account sinkage, heel and trim, is below the lower edge of any opening through which progressive downflooding may take place.
- The angle of heel due to unsymmetrical flooding does not exceed 15 degrees. If no part of the deck is immersed, an angle of heel of up to 17 degrees may be accepted.
- The metacentric height in the flooded condition is positive.
- As per condition of equillibrium for TYPE B SHIPS in Loadline convenion.
- shall have sufficient strength to withstand flooding of any one cargo hold to the water level outside the ship in that flooded condition in all loading and ballast conditions, taking also into account dynamic effects resulting from the presence of water in the hold,
- Prior to loading bulk cargo on bulk carriers of 150 m in length and upwards,
the shipper shall declare the density of the cargo, in addition to providing the
cargo information required by regulation
VI/2.
- shall be fitted with a loading instrument capable of providing information on hull girder shear forces and bending moments,
- shall be fitted with water level detector
- in each cargo hold, giving audible and visual alarms, one when the water level above the inner bottom in any hold reaches a height of 0.5 m and another at a height not less than 15% of the depth of the cargo hold but not more than 2 m.
- For cargo holds which are used for water ballast, an alarm overriding device may be installed. The visual alarms shall clearly discriminate between the two different water levels detected in each hold;
- in any ballast tank forward of the collision bulkhead required by regulation II-1/12 (now II-1/9), giving an audible and visual alarm when the liquid in the tank reaches a level not exceeding 10% of the tank capacity. An alarm overriding device may be installed to be activated when the tank is in use;
- In any dry or void space other than a chain cable locker, any part of which extends forward of the foremost cargo hold, giving an audible and visual alarm at a water level of 0.1 m above the deck.
- Such alarms need not be provided in enclosed spaces the volume of which does not exceed 0.1% of the ship’s maximum displacement volume.
- The audible and visual alarms specified in paragraph 1 shall be located on the navigation bridge.
- On bulk carriers, the means for draining and pumping ballast tanks forward of the collision bulkhead and bilges of dry spaces any part of which extends forward of the foremost cargo hold shall be capable of being brought into operation from a readily accessible enclosed space, the location of which is accessible from the navigation bridge or propulsion machinery control position without traversing exposed freeboard or superstructure decks.
Bulk carriers of 150 m in length and upwards of single-side skin construction,
carrying solid bulk cargoes having a density of 1,780 kg/m3 and
above, constructed before 1 July 1999 shall
- when loaded to the summer load line, be able to withstand flooding of the foremost cargo hold in all loading conditions and remain afloat with following stability criteria,
- The final waterline after flooding, taking into account sinkage, heel and trim, is below the lower edge of any opening through which progressive downflooding may take place.
- The angle of heel due to unsymmetrical flooding does not exceed 15 degrees. If no part of the deck is immersed, an angle of heel of up to 17 degrees may be accepted.
- The metacentric height in the flooded condition is positive.
- As per condition of equillibrium for TYPE B SHIPS in Loadline convenion.
- The transverse watertight bulkhead between the two foremost cargo holds and the double bottom of the foremost cargo hold shall have sufficient strength to withstand flooding of the foremost cargo hold, taking also into account dynamic effects resulting from the presence of water in the hold.
- if the bulk heads are not sufficiently strengthened,then,while carrying cargoes of density>1780 kg/m3,restrictions on the distribution of the total cargo weight between the cargo holds; and restrictions on the maximum deadweight.
- Any restrictions imposed on the carriage of solid bulk cargoes having a density of 1,780 kg/m3 and above shall be identified and recorded in the stability booklet/loading manual.
- Any bulk carrier to which above restriction applies,shall be permanently marked on the side shell at midships, port and starboard, with a solid equilateral triangle having sides of 500 mm and its apex 300 mm below the deck line, and painted a contrasting colour to that of the hull.
- Bulk carriers of 150 m in length and upwards of single-side skin construction, carrying cargoes having a density of 1,780 kg/m3 and above,if not complying with damage stability and structural strength criteria(of side structures) of IMO,then she shall not sail with any hold loaded to less than 10% of the hold’s maximum allowable cargo weight when in the full load condition, after reaching 10 years of age. The applicable full load condition for this regulation is a load equal to or greater than 90% of the ship’s deadweight at the relevant assigned freeboard.
SURVEYS AS REQUIRED AS PER SOLAS CHAPTER XII
Bulk carriers of 150 m in length and upwards of single-side skin construction,
constructed before 1 July 1999, of 10 years of age and over, shall not carry
solid bulk cargoes having a density of 1,780 kg/m3 and above unless
they have satisfactorily undergone either:
.1.
a periodical survey, in accordance with the enhanced programme of inspections
during ENHANCED surveys or
.2.
a survey of all cargo holds to the same extent as required for periodical
surveys in the enhanced programme of inspections during enhanced survey
-
Bulk carriers shall comply with the maintenance requirements provided in regulation II-1/3-1 and the Standards for owners’ inspection and maintenance of bulk carrier hatch covers, adopted by the Organization by resolution MSC.169(79) such as below.
1 Application
. These Standards define requirements for the owners’ inspection and maintenance of cargo hatch covers on board bulk carriers.2 Maintenance of hatch covers and hatch opening, closing, securing and sealing systems
2.1. Lack of weathertightness may be attributed to:.1. normal wear and tear of the hatch cover system: deformation of the hatch coaming or cover due to impact; wear of the friction pads where fitted; wear and tear of the cleating arrangement; or.2. lack of maintenance: corrosion of plating and stiffeners due to breakdown of coatings; lack of lubrication of moving parts; cleats, joint gaskets and rubber pads in need of replacement, or replaced with incorrect specification parts.2.2. Insecure hatch covers may be particularly attributed to damage or wear of securing devices, or incorrect adjustment, and incorrect pre-tension and load sharing, of cleating systems.2.3. Ship owners and operators shall therefore institute a programme of maintenance. This maintenance shall be directed to:.1. protecting exposed surfaces of plating and stiffeners of hatch covers and coamings in order to preserve overall structural strength;.2. preserving the surface of trackways of rolling covers, and of compression bars and other steel work bearing on seals or friction pads, noting that surface smoothness and correct profile are important for reducing wear rates on these components;.3. maintaining hydraulic or mechanically powered opening, closing, securing or cleating systems in accordance with manufacturer’s recommendations;.4. maintaining manual cleats in adjustment, with replacement when significant wastage, wear or loss of adjustment capability is identified;.5. replacing seals and other wear components in accordance with manufacturers’ recommendations, noting the need to carry on board or obtain such spares of correct specification, and that seals are designed for a particular degree of compression, hardness, chemical and wear resistance; and.6. keeping all hatch cover drains and their non-return valves, where fitted, in working order, noting that any drains fitted to the inboard side of seal lines will have non-return valves for prevention of water ingress to holds in the event of boarding seas.2.4. The equalization of securing loads shall be maintained following the renewal of components such as seals, rubber washers, peripheral and cross joint cleats.2.5. Ship owners and operators shall keep a Maintenance Plan and a record of maintenance and component replacement carried out, in order to facilitate maintenance planning and statutory surveys by the Administration. Hatch cover maintenance plans shall form part of a ship’s safety management system as referred to in the ISM Code.2.6. Where the range of cargoes carried requires different gasket materials, a selection of gasket materials of the correct specifications shall be carried on board, in addition to other spares.2.7. At each operation of a hatch cover, the cover and, in particular, bearing surfaces and drainage channels shall be free of debris and as clean as practicable.2.8. Attention is drawn to the dangers of proceeding to sea without fully secured hatch covers. Securing of all covers shall always be completed before the commencement of a sea passage. During voyages, especially on loaded passages, cover securing devices and tightness of cleating and securing arrangements shall be checked, especially in anticipation of, and following periods of, severe weather. Hatch covers may only be opened on passage, when necessary, during favourable sea and weather conditions; imminent weather forecasts shall also be considered.2.9. Operators shall consult the Cargo Securing Manual when planning the loading of containers or other cargo on hatch covers and confirm that they are designed and approved for such loads. Lashings shall not be secured to the covers or coamings unless these are suitable to withstand the lashing forces.3 Inspection of hatch covers and hatch opening, closing, securing and sealing systems
3.1. Statutory surveys of hatch covers and their coamings are carried out by the Administration as part of the annual survey required by article 14 of the International Convention on Load Lines, 1966, as modified by the 1988 Protocol relating thereto and in accordance with the requirements for Enhanced Surveys contained in resolution A.744(18), as amended. However, the continued safe operation is dependent on the shipowner or operator instituting a regular programme of inspections to confirm the state of the hatch covers in between surveys.3.2. Routines shall be established to perform checks during the voyage, and inspections when the hatch covers are opened.3.3. Voyage checks shall consist of an external examination of the closed hatch covers and securing arrangements in anticipation of, and after, heavy weather but in any event at least once a week, weather permitting. Particular attention shall be paid to the condition of hatch covers in the forward 25% of the ship’s length, where sea loads are normally greatest.3.4. The following items, where provided, shall be inspected for each hatch cover set when the hatch covers are opened or are otherwise accessible on each voyage cycle, but need not be inspected more frequently than once per month:.1. hatch cover panels, including side plates, and stiffener attachments of opened coversfor visible corrosion, cracks or deformation;.2. sealing arrangements of perimeter and cross joints (gaskets, flexible seals on combination carriers, gasket lips, compression bars, drainage channels and non-return valves) for condition and permanent deformation;.3. clamping devices, retaining bars and cleating for wastage, adjustment, and condition of rubber components;.4. closed cover locating devices for distortion and attachment;.5. chain or wire rope pulleys;.6. guides;.7. guide rails and track wheels;.8. stoppers;.9. wires, chains, tensioners and gypsies;.10. hydraulic system, electrical safety devices and interlocks; and.11. end and inter-panel hinges, pins and stools where fitted.As part of this inspection, the coamings with their plating, stiffeners and brackets shall be checked at each hatchway for visible corrosion, cracks and deformation, especially of the coaming tops and corners, adjacent deck plating and brackets.